
Y O U
R P U B L I C
L Y - O W N E D
E L E C T R I C
U T I L I T Y
RESIDENTIAL SERVICE
REQUIREMENTS

INTRODUCTION TO
TEMPORARY SERVICES
Where poles with transformers are adjacent to or near your project, you
should request temporary overhead service (see Figure B-1).
If the electrical
facilities in your area are underground, you will need to install a temporary
underground meter pedestal to obtain temporary power. If there is power in your
area but the power lines are not visible, it is likely to be underground. Refer
to SECTION C for more information on underground service.
The process and cost of obtaining your temporary overhead service can vary depending upon the location of our existing facilities. The least complicated and cheapest way a service can be installed is if a transformer is located on a pole on or along your property.
If you are in an overhead area, but will have a permanent underground meter base and you want to install the conduit and trench now, refer to SECTION C. In this case your temporary underground meter base must be installed within two feet of the service hand-hole.
If you are in an underground area, you must have an underground temporary service (see Figures B-3 and B-4).
Other installations are more complicated. All installations are reviewed by Central Lincoln. Please speak with one of our engineering technicians if you have any questions.
There is a processing fee to connect a temporary service. If any engineering is required, additional costs may be incurred.
OVERHEAD METER LOCATION
Your temporary meter post should be located on your property. Install the
meter post as close as 6 (preferred) to the Central Lincoln pole, but no
more than 100 from the pole that will serve you. The reason for this limitation
is ensuring that your temporary service pole can withstand the weight of the
conductor. If a distance greater than 100 is required, please contact your
local service office and ask an engineering technician for approval prior to
construction. A taller, stouter post with additional bracing could be required.
In addition to the distance limitation mentioned above, please consider the following:
If you have any questions, please contact us.
OVERHEAD CLEARANCE
REQUIREMENTS
The National Electric Code (NEC) and the National Electric Safety Code
(NESC)
have established minimum clearance requirements to maintain safe height distance
for electrical conductors over various terrain.
The NEC and NESC require the lowest point of a service conductor to be at least 12 feet 6 inches above the ground. The bottom of the drip loop must be a minimum of 10 feet 6 inches above the ground (see Figure B-2). NOTE: Clearance over any driveway must be at least 18 feet.
Figure E-2 (Section E - Existing Overhead Service) shows the clearance requirements for the types of terrain most commonly encountered. These clearances apply to both permanent and temporary weatherheads.
It is not your responsibility to provide and install the conductor, but you are required to provide a point of attachment at your service post that will allow Central Lincoln to meet the clearance requirements.
If you need further detail, please consult the current issue of the NEC or contact the local electrical inspection agency (see SECTION A - General Information).
OVERHEAD SERVICE
INSTALLATION
The following items must be completed before we can energize your service:
Figure B-2 is a drawing of the standard temporary overhead service installation recommended by Central Lincoln. The specifications given are the minimum acceptable.
Items owned/installed by the customer (Figure B-2)
A 6" x 6" x 16 minimum, continuous, single structure, pressure treated, firmly set and drilled with an 11/16" hole 6" below top of pole in line with service drop.1.
Items owned and installed by
CLPUD (Figure B-2)
7. Meter.
UNDERGROUND METER LOCATION
The following items are required to properly locate your meter pedestal:
UNDERGROUND SERVICE
INSTALLATION
The following items must be completed prior to energizing your service:
UNDERGROUND METER BASE
REQUIREMENTS
It is your responsibility to provide a buried cable from your meter base to
our transformer or hand-hole.
The requirements to connect to an overhead converted to underground meter pedestal are shown in Figure B-3. The cable you install should be sized per the NEC and should have a minimum cover of 24".
If our connection point is a hand-hole or transformer, trench to our nearest service location and leave your wires exposed. If you discover any other conductors while digging your trench, please leave them covered. Remember, do not install conduit or elbows inside the transformer or transformer substructure without Central Lincoln direct supervision and assistance.
REMINDER: You are required to call the "One Call" system (811) and request buried utility locations at least 2 business days before digging. Any trenching within 24" of existing underground facilities must be done by hand.
Figure B-4 illustrates an underground temporary meter pedestal
installation. Please note the dimensions shown. Deviations from these
recommended standards could result in a delay in receiving your service and/or
your service being denied. Please contact us if you have any questions.
Items owned/installed by the customer (Figs. B-3,
B-4)
A 6" x 6", continuous, single structure, firmly set.1.
Items owned and
installed by CLPUD (Figs. B-3,
B-4)
7. Meter
8. Service Line
Back to Contents To Next Chapter To Home Page
If you have questions, comments or suggestions, please e-mail us at webmaster@cencoast.com.